Dear ENKA Employees,
The latest news and updates on ENKA Quality Management System are presented for your information in this newsletter.
2025 Internal Audit Schedule,
We announce you the approved and updated Internal Audit Schedule for 2025.
Two of our projects have been included in the 2025 Internal Audit Schedule:
- MZ305 – Mozambique Rovuma LNG Phase 1 FEED Project
- TR225 – Tuzla Data Center
Audit dates have been revised for three (3) project / subsidiary audits:
- 02031 Special Project
- 02034 Special Project
- ENKA Power
Project and subsidiary audits within the scope of the Internal Audit Schedule are carried out by auditors from the Corporate Quality, Financial Control, Sustainability, Ethics and Compliance, Information Security, Information Technologies, Human Resources, Legal and Machinery & Equipment Management teams.
You can access the updated Audit Schedule via the link below:
March 2025 – Internal Audits Conducted
The second and third audits of the 2025 Internal Audit Schedule were carried out in the week of March 17-21 in the following projects:
- DE303 – Dradenau CHP (Uniper-ENKA JV)
- DE401 – Dradenau CHP Mechanical
Detailed internal audit reports including the findings and areas of improvement related to the audits will be created and shared with the relevant management teams.
April 2025 – External Audits to be Conducted
BSI Assessment Audit
As part of our ongoing commitment to excellence in quality management, and in line with BSI’s annual continuous assessment for the maintenance of ENKA’s ISO 9001 certification, the annual BSI ISO 9001 audit will be conducted at the Morovo Corridor Highway Project from April 7 to April 10, 2025.
The audit will assess the compliance of ENKA’s Quality Management System with the ISO 9001 Quality Management Standard. Each year, a different project is selected to exemplify our implementation of this standard.
Audit Objective:
The objective of the assessment is to conduct a surveillance assessment and look for positive evidence to ensure the elements of the scope of certification and the requirements of the management standard are effectively addressed by the organization’s management system and that the system is demonstrating the ability to support the achievement of statutory, regulatory and contractual requirements and the organization’s specified objectives, as applicable with regard to the scope of the management standard, and to confirm the ongoing achievement and applicability of the forward strategic plan.
This audit is a valuable opportunity to reaffirm our commitment to quality and continuous improvement. We sincerely appreciate the cooperation and support of all teams involved in this process.